Deployment playbookv0.1 · 29 Oct 2026
Digitize growing areas & primary processing facilities
ECO-MEND — Package 1. A deployment roadmap from preparation, configuration, and training to independent operation, acceptance, and handover.
15 working days7 phases5 data-entry engineers
Deployment framework
Fields marked [FILL IN] are completed by the project team for each customer; items marked [TO BE AGREED] must be agreed before use. Feature references follow the Ecomend System Feature List.
1. Project information
| Item | Details |
|---|---|
| Product / package | Ecomend — Package 1 [TO BE AGREED: commercial name of the package] |
| Objective | Deploy Package 1 for the customer and sign off on acceptance |
| Customer · location | [FILL IN] |
| Customer contact | [FILL IN] · [FILL IN] |
| PM · Ops | [FILL IN] · [FILL IN] |
| Users | 5 data-entry engineers: [n] for growing areas, [n] for primary processing facilities/quality control (QC), [n] admins |
| Standard duration | 15 working days (N1–N15); the start date is agreed by the parties. |
| Start date N1 · acceptance sign-off date | [FILL IN] · [FILL IN] |
| Version | v0.1 — 29/10/2026 (framework draft) |