Deployment playbookv0.1 · 29 Oct 2026

Digitize growing areas & primary processing facilities

ECO-MEND — Package 1. A deployment roadmap from preparation, configuration, and training to independent operation, acceptance, and handover.

15 working days7 phases5 data-entry engineers
Deployment framework

Fields marked [FILL IN] are completed by the project team for each customer; items marked [TO BE AGREED] must be agreed before use. Feature references follow the Ecomend System Feature List.

1. Project information

1. Project information
ItemDetails
Product / packageEcomend — Package 1 [TO BE AGREED: commercial name of the package]
ObjectiveDeploy Package 1 for the customer and sign off on acceptance
Customer · location[FILL IN]
Customer contact[FILL IN] · [FILL IN]
PM · Ops[FILL IN] · [FILL IN]
Users5 data-entry engineers: [n] for growing areas, [n] for primary processing facilities/quality control (QC), [n] admins
Standard duration15 working days (N1–N15); the start date is agreed by the parties.
Start date N1 · acceptance sign-off date[FILL IN] · [FILL IN]
Versionv0.1 — 29/10/2026 (framework draft)